Tier III Global Data Center Expansion
Retail Chain Client
Project Scope: Stand Alone Data Center Engineering Design & Commissioning Services
Project Size: 20,000 sq. ft.
Raised Floor: 10,000 sq. ft.
Tier Classification: III
Watts per SF: 90 w/sq. ft.
Redundancy: 2N
Diesel Generator: (4) N+1 / 1,500 kW
UPS System: (2) 2 N / 625 kVA
Total Constuction: $15 Million
|